Bodur, İbrahim Volkan2016-01-082016-01-081990http://hdl.handle.net/11693/17273Ankara : The Department of Management and the Graduate School of Business Administration of Bilkent Univ., 1990.Thesis (Master's) -- Bilkent University, 1990.Includes bibliographical references leaves 35-36.Critical Path Method (CPM) is an economic and useful tool to aid managers during preparation and application of projects for scheduling, giving control and coordination, and solving the problems. In this study, CPM is applied to İzmir Winery Wastewater Treatment Plant. A schedule is calculated by CPM and its network diagram and bar chart of ,works is prepared with the Primavera Project Planner which-is a project management and control software.vi, 80 leavesEnglishinfo:eu-repo/semantics/openAccesscritical path methodplanning and schedulingwastewater treatment plantTS158 .B63 1990Critical path analysis.Sewage disposal plants.Utilization of critical path method in the planning of İzmir Winery Wastewater Treatment PlantThesis